Signed in as:
filler@godaddy.com
Signed in as:
filler@godaddy.com
Topics include:
City Council meeting documents and videos can be found at:
https://bluelake.ca.gov/city-council/agendas-minutes/
The City of Blue Lake has been out of compliance with State Housing Element Law since August 31, 2009. The current City Council adopted the Sixth Cycle Housing Element Update on July 22, 2025 and has authorized the City Manager to apply for a CDBG grant to fund the work needed to update the Housing element for the Seventh Cycle by the due date of August 31, 2027.
The following are documents and video resources regarding this process.
Summary contained in Blue Lake City Council Resolution 1244 Adopted on 12/02/2025:
WHEREAS, by letter dated January 24, 2020,HCD reminded the City of Blue Lake
(“City”) that it was required to revise its Sixth Cycle Housing Element pursuant to
Government Code Section 65588 by August 31, 2019, and notified the City that it had been
out of compliance with Housing Element Law since August 31, 2009; and
WHEREAS, on December 8, 2020, the City entered into a Standard Agreement with HCD
for Local Early Action Planning (LEAP) grant funding to assist with preparation of an
updated Housing Element for the Sixth Cycle; and
WHEREAS, HCD continued to correspond with the City in 2021 and 2022 regarding the
need to achieve Housing Element compliance, including by letters dated November 23,
2021, and April 27, 2022; and
WHEREAS, on May 31, 2022, the City submitted its first draft Sixth Cycle Housing
Element to HCD, and on August 29, 2022, HCD provided written comments identifying
necessary revisions to achieve compliance; and
WHEREAS, on October 18, 2022, the City received Regional Early Action Planning
(REAP) grant funding to prepare a CEQA Initial Study to support adoption of its Sixth
Cycle Housing Element; and
WHEREAS, following continued coordination, the City submitted revised drafts to HCD
on April 28, 2023, and August 28, 2023; and
WHEREAS, on September 23, 2023, HCD informed the City that its Housing Element met
statutory requirements; however,consistent with Government Code Section 65588(e)(4),
it could not be deemed in substantial compliance until the City completed required rezoning
under Program HI-14; and
WHEREAS, on January 28, 2025, the City submitted a draft combining zone to implement
Program HI-14, and on February 6, 2025, HCD provided feedback and recommended
revisions to ensure compliance with State Housing Law; and
WHEREAS, following additional correspondence on April 30 and May 28, 2025, regarding
the timeline for completing rezones and achieving compliance, HCD issued a Notice of
Violation on June 27, 2025, and rejected the City’s proposed completion date of February
2026; and
WHEREAS, on June 30, 2025, the City provided an updated and accelerated compliance
timeline proposing to complete all required actions by December 15, 2025; and
WHEREAS, on July 22, 2025, the City Council adopted the Sixth Cycle Housing Element
Update after a duly noticed public hearing, and on July 30, 2025, submitted the adopted
Element and associated Sites Inventory to HCD; and
WHEREAS, on August 21, 2025, HCD advised the City that substantial compliance would
not be recognized until completion of rezoning actions necessary to meet both Fifth and
Sixth Cycle RHNA obligations and implementation of Programs HI-1 through HI-23; and
WHEREAS, to avoid referral to the Office of the Attorney General and in exchange for
HCD’s forbearance from pursuing penalties or litigation for past noncompliance, the City
and HCD have negotiated a Memorandum of Understanding (MOU) setting forth specific
timelines, obligations, and remedies for achieving full compliance with Housing Element
Law; and
WHEREAS, the City Council finds that execution of the MOU is in the best interests of
the City and its residents, as it provides a clear and enforceable path to compliance, protects
the City’s eligibility for State funding, and avoids potential enforcement actions and
financial penalties.
Presentation of final steps to complete the 6th cycle Housing Element update 12/2/25.
Coming Soon: A Deep Dive into the last 5 years of work on the Housing Element.

Audio recording - City Council Meeting 11/19/25 - State of the Bike Park & MOU with RCMBA
One of the most striking revelations is that no official project-level approval was ever granted by the City Council. While a conceptual endorsement of a bike park idea was discussed in past meetings, the actual construction, scope, costs, and vendor engagements were never formally reviewed or authorized by council through a public vote. This lack of approval undermines the transparency and legitimacy of the entire project.
The city currently owes more than $132,000 to vendors for work that was never authorized as part of the city’s adopted budget. This includes substantial sums for grading, construction, materials, and project management. These expenses bypassed the council’s financial oversight, suggesting that significant financial decisions were made without authority.
Councilmembers and the public were repeatedly told that the city only spent $7,000 for the bike park, when in fact over $130,000 in unpaid services had already accrued. Multiple councilmembers recalled asking for financial breakdowns earlier in the year (including in March and April), but those requests were ignored or deferred. As one councilmember put it: "The public asked directly and we were lied to."
City Resolution 1077 requires that any donation over $5,000 must come before the council for review and acceptance. Despite this, several large donations — including two $10,000, and over $36,000 from the Redwood Coast Mountain Bike Association (RCMBA) — were not approved, publicly acknowledged or properly accepted according to policy. This failure violated city transparency rules and disrespected both donors and taxpayers.
The City has acknowledged that all work completed so far was based on conceptual designs, not engineered plans. There are no stamped blueprints, no verified compaction studies, and no records of proper inspections during or after the work was performed. This means the current state of the bike park could pose serious safety, liability, and environmental risks. As one official put it: “We have to figure out what’s actually out there.”
Portions of the park may have involved grading and land disturbance beyond what was permitted, and no clear documentation shows that the project underwent environmental review or planning commission oversight. The City is now considering backtracking through permits and possibly commissioning "as-built" reports to understand what was actually done — a costly and embarrassing scenario for a publicly funded project.
Several vendors were engaged for major work — including Wildland Operators, without evidence of competitive bidding, formal contracts, or clear scopes of work. This lack of documentation is highly irregular, especially for public projects, and violates standard procurement laws. It also creates confusion over who authorized the work, and whether the City is legally obligated to pay outstanding bills.
Councilmembers repeatedly asked who was managing the project, who hired the vendors, and whether any contracts were reviewed by city legal staff. No answers were provided during the meeting. It remains unclear whether former staff, local associations, or private individuals were directing public funds or assets without oversight.
Some invoices submitted were for work done 6 to 12 months previously, with vague or incomplete descriptions. In one case, a $10,000 bill was submitted for landscaping work, but no landscaping appears to have been done at the park. In another, a $5,000 “donation” was assumed to cover an invoice, but it was later revealed that it did not apply to the City’s balance. These inconsistencies raise questions about fraud, miscommunication, or manipulation of public resources.
Perhaps the most damaging of all — the public was repeatedly given false assurances that the bike park was nearly complete and financially sound, even as unpaid bills piled up. Residents who asked hard questions were dismissed or ignored. Now, after months of confusion, the truth has surfaced — and the damage to public trust is substantial. The current council is now left to pick up the pieces, assess safety risks, and decide how to finish a project that was supposed to bring the community together.
Committee to Oppose the Recall of Elise Scafani
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.